Reference No. WB/MOF/MINIS/CS/001-1/2012

Activity Title: Individual International Consultant to provide technical support to the Working Group for Feasibility Study of "Orkhon-Gobi" Project

Proc. Type and Method: Selection of Individual Consultant


Awarded to:
- Mr. Evgeny Simonov

Duration of contract: 1 month

Date of Award: 18 June 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the "Orkhon-Gobi" Project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Reference No. WB/MOF/MINIS/CS/001-2/2012

Activity Title: Individual Local Consultant to provide technical support to the Working Group for Feasibility Study of "Orkhon-Gobi" Project

Proc. Type and Method: Selection of Individual Consultant

Awarded to:
- Mr. Ulziijargal Lochin

Duration of contract: 1.5 month

Date of Award: 18 June 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the "Orkhon-Gobi" Project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Reference No. WB/MOF/MINIS/CS/002-1/2012

Activity Title: Individual International Consultant to provide technical support to the Working Group for Feasibility Study of "Comprehensive management and monitoring system based on high speed broadband” Project

Proc. Type and Method: Selection of Individual Consultant

Awarded to:
- Mr. Ronald. N. Box

Duration of contract: 21 days

Date of Award: 21 June 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the "Comprehensive management and monitoring system based on high speed broadband” Project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Reference No. WB/MOF/MINIS/CS/002-2/2012

Activity Title: Individual Local Consultant to provide technical support to the Working Group for Feasibility Study of "Comprehensive management and monitoring system based on high speed broadband” Project

Proc. Type and Method: Selection of Individual Consultant

Awarded to:
- Mr. Enkhtsog Dagvadorj

Duration of contract: 2 months

Date of Award: 21 June 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the "Comprehensive management and monitoring system based on high speed broadband” Project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Reference No. WB/MOF/MINIS/CS/003-1/2012

Activity Title: Individual International Consultant to provide technical support to the Working Group for Feasibility Study of "Integrated Steel Complex with Infrastructure" Project

Proc. Type and Method: Selection of Individual Consultant

Awarded to:
- Mr. Jörg Overländer

Duration of contract: 6 weeks

Date of Award: 4 July 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the “integrated steel complex with infrastructure” project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Reference No. WB/MOF/MINIS/CS/003-2/2012

Activity Title: Individual Local Consultant to provide technical support to the Working Group for Feasibility Study of "Integrated Steel Complex with Infrastructure" Project

Proc. Type and Method: Selection of Individual Consultant

Awarded to:
- Mr. Dashdondog Yamaaranz

Duration of contract: 2 months

Date of Award: 4 July 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the “integrated steel complex with infrastructure” project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Reference No. WB/MOF/MINIS/CS/004-1/2012

Activity Title: Individual International Consultant to provide technical support to the Working Group for Feasibility Study of "Shuren Hydropower Plant" Project

Proc. Type and Method: Selection of Individual Consultant

Awarded to:
- Mr. Bryan Leyland

Duration of contract: 28 days

Date of Award: 4 July 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the "Shuren HPP" project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Reference No. WB/MOF/MINIS/CS/004-2/2012

Activity Title: Individual Local Consultant to provide technical support to the Working Group for Feasibility Study of "Shuren Hydropower Plant" Project

Proc. Type and Method: Selection of Individual Consultant

Awarded to:
- Mr. Boldbaatar Burentsagaan

Duration of contract: 2 months

Date of Award: 4 July 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the "Shuren HPP" project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Reference No. WB/MOF/MINIS/CS/005-1/2012

Activity Title: Individual International Consultant to provide technical support to the Working Group for Feasibility Study of "Khuut-Bichigt" of Phase II and Pre-Feasibility Study of Phase III under State Policy on Railway Transportation

Proc. Type and Method: Selection of Individual Consultant

Awarded to:
- Mr. Daniel B. Mesnick

Duration of contract: 24 days

Date of Award: 6 July 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the "Khuut-Bichigt" of Phase II and Pre-Feasibility Study of Phase III project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Reference No. WB/MOF/MINIS/CS/005-2/2012

Activity Title: Individual Local Consultant to provide technical support to the Working Group for Feasibility Study of "Khuut-Bichigt" of Phase II and Pre-Feasibility Study of Phase III under State Policy on Railway Transportation

Proc. Type and Method: Selection of Individual Consultant

Awarded to:
- Mr. Gotov Dugerjav

Duration of contract: 2 months

Date of Award: 6 July 2012


SCOPE OF THE SERVICE :

The main objective of this assignment is to assist the Working Group determine the studies that should be carried out to prepare the feasibility study for the "Khuut-Bichigt" of Phase II and Pre-Feasibility Study of Phase III project, assess the appropriateness of existing TORs for the feasibility study, define the timing and sequencing of remaining studies, and finalize the TORs to select the firm to prepare and finalize the TOR for the feasibility study.

Share:
minis

MINIS